View Summary Level Planning Packages (SLPP) Remaining Budget

You can view the SLPP remaining budget on the properties page of summary planning package.

Viewing SLPPs With Remaining Budget

When an SLPP balance goes down to zero, the SLPP has no remaining budget. The summary planning package list page displays SLPPs having a budget greater than zero. To view all SLPPs, set the Has Remaining Budget filter field to All and filter the list.

See the CA Clarity Basics User Guide for more information.

Follow these steps:

  1. Open the contract.

    The properties page appears.

  2. Click Contract WBS.

    The contract WBS page appears.

  3. Expand the CWBS hierarchy to locate the CWBS element for the SLPP, and then click the name of the CWBS element.

    The properties page appears.

  4. Click Summary Planning Packages.

    The list page appears.

  5. Click the name of the SLPP.

    The properties page appears, displaying the remaining budget (BAC) in the Budget field.