Manually Reduce SLPP Budget

Specify the budget amount to be drawn from the SLPP into the work package. Then, manually reduce the SLPP budget by the amount you entered in the work package. Use the Budget field on the properties page of summary planning package to report the amount.

Follow these steps:

  1. Open the contract.

    The properties page appears.

  2. Click Contract WBS.

    The WBS contract page appears.

  3. Expand the CWBS hierarchy to locate the CWBS element for the SLPP, and then click the name of the CWBS element.

    The properties page appears.

  4. Click Summary Planning Packages.

    The list page appears.

  5. Click the name of the SLPP to reduce the budget.

    The properties page appears.

  6. Edit the remaining budget (BAC) in the Budget field, and save.

    The SLPP budget is reduced by the amount you are drawing down.