Previous Topic: Create New Contract Baselines

Next Topic: Edit Baselines (Contracts)

Define which Baseline is Current

The baseline last created becomes the current contract baseline, by default. If you have defined only one baseline, the baseline is marked as the current baseline. To change the current baseline, open the baseline, select the Current Revision field, and save the baseline revision.

The current contract baseline is used to display data on the properties page of contract pricing and on the CPR reports. For example, the CPR Format 3 report displays baseline data at the beginning and end of the reporting period, and lists all the baselines between those two dates.

Follow these steps:

  1. Open the contract.

    The properties page appears.

  2. Click Baseline.

    The contract baseline properties page appears.

  3. Open the baseline.

    The baseline revision properties page appears.

  4. Select the Current Revision field, and save.

More information:

Contract Performance Report (CPR) Format 3 - Baseline