Follow these steps:
The programs page appears.
The create page appears.
Specifies the pool of resources allowed when assigning resources to programs.
Values:
Default: Resource Pool
Required: Yes
Required. Enter a unique name for the program.
Limit: 80 characters
Required. Enter a unique ID for the program.
Limit: 20 characters
Enter a description of the program.
Limit: 254 characters
This fields defaults to the name of the user creating the program.
Required. Select the Dashboard layout to view project or program data.
Values:
See the PMO Accelerator Product Guide for more information.
Select or enter the date of starting the program.
Select or enter the date of completing the program.
Defines the company-defined stage for the program.
Select a goal for the program.
Values: Cost Avoidance, Cost Reduction, Grow the Business, Infrastructure Improvement, and Maintain the Business.
This field is only applicable if you plan to work with the project in Open Workbench. The number entered is a score for the importance of the project in relation to all other projects in your organization. This score controls the order in which tasks are scheduled during Autoschedule, subject to dependency constraints.
Values: 0-36, with 0 being the highest.
Default: 10
Select the program progress.
Values: Completed, Started, and Not Started.
Default: Not Started.
Select the program status.
Values: Approved, Unapproved, and Rejected.
Default: Unapproved.
Specifies the method for calculating the percent complete value for the project and tasks.
Note: If you are using CA Clarity PPM with Microsoft Project, or if you are using an external job to calculate % Complete, select manual as the calculation method.
Values:
Summary Task % Complete = Total Detail Task Duration Complete / Total Detail Task Duration
Summary Task % Complete = Sum of Detail Task resource assignment Actuals / Sum of Detail Task resource assignment Effort Detail Task % Complete = Sum of resource assignment Actuals / Sum of resource assignment Effort
Note: If you assign a non-labor resource to a task and the % Complete Calculation Method is set to Effort, the effort and actuals for that resource are ignored in the calculation.
Default: Manual
In the Organizational Breakdown Structures section, define the OBS to associate with the program for security, organizational, or reporting purposes.
Defines the financial department associated with the program.
Required: No
Defines the financial location associated with the program. The location requires belonging to the same entity as the department.
| Copyright © 2011 CA. All rights reserved. | Tell Technical Publications how we can improve this information |