You can open the legend from the Gantt View toolbar. The Gantt chart displays the following indicators to specify the type or status of a task:
|
Indicator |
Description |
|---|---|
|
|
Task. A task is an activity that is required to be accomplished within a time frame. Tasks define the project work, the staff member, and the resource that performs the work. |
|
|
Progress Through Bar |
|
|
Completed Task. A completed task is a task where its status is set to "Completed". |
|
|
Late Task. A late task is a task or milestone where the Finish date field value is later than the Baseline Finish date field value. |
|
|
Summary Task. A summary task is a task that has one or more subtasks nested beneath it. |
|
|
External Task displayed in the Gantt chart. An external task is a task in another project on which a task within the project has a dependency. |
|
|
Subproject displayed in the Gantt chart. A subproject is a project located within a master project. |
|
|
External Task displayed in the WBS. An external task is a task in another project on which a task within the project has a dependency. |
|
|
Subproject displayed in the WBS. A subproject is a project located within a master project. |
|
|
Milestone. Milestones are tasks that have a due date but not a duration (a period between a start and finish date). |
|
|
Completed task. A completed task is a task where its status is set to "Completed". |
|
|
Late task. A late task is a task or milestone where the Finish date field value is later than the Baseline Finish date field value. |
|
|
External Milestone. An external milestone task is a milestone in another project on which a task within the project has a dependency. |
|
|
Critical Path. The critical path determines the earliest finish date of the project. |
|
|
Link to hidden task. |
You can change the Gantt chart timescale as needed so that you can zoom in and out of the timeline. Click the single arrow at the top left or right of the Gantt chart to scroll one time unit at a time. Or, click the double arrows to jump to the next set of time periods.
Follow these steps:
The properties page appears.
The Gantt view appears.
The Gantt timescale changes based on your selection.