How to Update Cost Totals

Update costs when you create or update a baseline, and when you change the task information - an input for earned value calculations. When earned value is used, update the total costs to view costs tied to ACWP, EAC (Cost), and ETC (T).

Use the following process to update the costs totals for your project:

  1. Schedule the Rate Matrix Extraction job to run periodically.

    Contact your CA Clarity PPM administrator or see the Administration Guide for more information.

  2. Do one of the following:

More information:

Task Cost Metrics

Create New Baselines (Investments)

Edit Baselines (Investments)