Use the following procedure to create a detailed risk. Suppose, you create a detailed risk and specify a risk category. The overall score from the risk overrides any differing status selection you make for the risk category or factor on the main risk page.
Follow these steps:
The risks page appears.
The create page appears.
Defines the short name for the risk. If you create a risk from a change request, the value for the field loads from the Change Request Name field. If you create a risk from an issue, the value for the field loads from the Issue Name field on the issue properties page.
Limit: 64 characters
Required: Yes
Defines the unique identifier for the risk. Once the risk is saved, you cannot change the identifier.
Required: Yes
Defines the short description of the risk. If you create a risk from a change request, the value for the field loads from the Description field on the change request properties page. If you create a risk from an issue, the value for the field loads from the Description field on the issue properties page.
Required: No
Defines the risk category to assign the risk. If you create a risk from a change request, the value for the field loads from the Category field on the change request properties page. If you create a risk from an issue, the value for the field loads from the Category field on the issue properties page.
Values: Objectives, Sponsorship, Funding, Resource Availability, Interdependencies, Technical, Human Interface, Organizational Culture, Supportability, Implementation, and Flexibility
Required: No
Defines the name of the resource who is managing the risk. This resource is responsible for verifying that the risk is managed and tracked appropriately through its lifecycle. If an issue or change request is created from this risk, the owner information is carried over to the issue or change request.
Default: The resource currently logged in
Required: Yes
Defines the priority level for this risk.
Values: Medium, Low, and High
Default: Low
Required: Yes
Specifies the status of this risk.
Values: Open, Work in Progress, Closed, or Resolved
Default: Open
Required: Yes
Displays the name of the resource who created this risk.
Default: The resource currently logged in
Displays the date this risk was created.
Displays the name of the resource who last updated this risk.
Default: The resource currently logged in
Displays the date this risk was last updated.
Defines the symptoms that identify this item as a risk.
Defines the description of the result this risk has on the project.
Defines the date by which repercussions from this risk could affect the project. If you identify an impact date, enter a date in the Target Resolution Date field.
Default: Current date
Defines the date the risk is targeted to be resolved - the date being the same or earlier than the impact date.
Default: Current date
Defines the assumptions that determine that this item could be a risk. You can verify these assumptions to help ensure that they continue to be valid through the duration of the risk life. If the assumptions change, the impact or probability of the risk can also change.
Defines the risks within this project that are associated with this risk. You can only link this risk to risks within this project.
Defines the issues within this project that are associated with this risk. You can only link this risk to risks within this project.
Defines the type of response you want to make with this risk.
Values:
Default: Watch
Defines the probability that the impact can occur. The risk probability is used to calculate the risk exposure.
Values: Low (1), Medium (2), or High (3)
Default: Low
Displays the score calculated based on the selections you make in the Probability and Impact fields.
Risk values:
Defines the effect of the particular risk on the project, determined by the risk effect on project performance, supportability, cost, and schedule. This value is used to calculate the risk exposure.
Values: Low (1), Medium (2), or High (3)
Default: Low
Specifies one or more attachments.
Defines the final resolution of this risk once the matter is resolved. The resolution data is useful for recalling the outcome of a risk response strategy when planning or approaching future project risk plans.
Required: No
Specifies the risks encountered or created within the project as a result of the mitigation taken to resolve the risk. Unlike associated risks, residual risks do not share similar outcomes, but result from an action you take in resolving a risk.