Use the following procedure to define a baseline revision as the current baseline. You can view the current baseline revision from the baseline properties page. A checkmark icon displays in the Current Revision field for the current revision. By default, the baseline you create last becomes the current project baseline. If you have defined only one baseline, that becomes the current baseline.
Follow these steps:
The properties page appears.
The baseline properties page appears.
Specifies to make this baseline the current baseline. The field is display only if a baseline revision exists.
Default: Selected
Select the check box.