Subproject Baselines

The master project baseline information is an aggregation of its own baseline information and subprojects. The baseline is dynamically aggregated at the time you set the baseline. The master project resource baseline information is an aggregation of the team baseline information.

More information:

How Master Project and Subproject Baselines Work

About Updating Master Project Baselines

Display Master Project Baselines

Baselines

Update Project Baselines

How to Calculate and Record Earned Value Totals