Refresh Project Data

If you are using Open Workbench with CA Clarity PPM, it is possible for other users to update information in CA Clarity PPM that affects the project you have open and locked in Open Workbench. To verify that you have the latest information, you can refresh certain types of information from your project open in Open Workbench with any updates made in CA Clarity PPM. You can refresh:

Project-specific information. To update all project data, you must have your project open in CA Clarity PPM in read/write mode. The options in the Options for [Project] section of the Update dialog box are unavailable if you open the project from CA Clarity PPM. Use the Update dialog box to determine what data you want to pull from CA Clarity PPM into your project in Open Workbench.

To refresh project information

  1. Select Update from the Clarity group in the Project ribbon.

    The Update dialog box appears.

  2. Select or clear the following check boxes:
    Calendars

    Specifies whether to refresh your project's current calendar with any changes made to the calendar in the CA Clarity PPM project.

    Note: Calendars are not specific to a resource.

    System Options

    Specifies whether to update your project's options, such as roles, and customized data mapping, with any changes made to the system options in CA Clarity PPM.

    Important! Selecting this option can change your working copy's default options.

  3. Select or clear the following check boxes in the Options For [Project] section:

    Note: You must have the project open in read/write mode to select or clear check boxes in this section.

    New Notes

    Specifies whether to include only the task notes created since the project was opened or last refreshed in the update.

    Example: Another user added a note to an unplanned task on their CA Clarity PPM timesheet while the project was locked in Open Workbench.

    Resources

    Refreshes all attributes for resources assigned to the project. Updates the project with revisions to resource data, such as updates to resource calendars. Assignment revisions, such as a change in the assignment estimate to complete (ETC), are not updated.

    Status

    Specifies whether to include changes to Actual Usage, Actual Thru, Pending Actuals, and Pending Estimates for assignments of the project in the update.

    New Tasks and Assignments

    Specifies whether to include new tasks and assignments that have been created since the project was opened or last refreshed in the update.

    Team Members

    Specifies whether to include changes to existing team members and bring in new team members that were added while you had the project locked in Open Workbench.

    Example: Another user added a new team member or updated an existing team member allocation, start date, or finish date while the project was locked in Open Workbench.

  4. Click OK.

    The Update dialog box closes and the information you selected is refreshed in your local copy of the project.

More information:

Manage CA Clarity PPM Projects using Open Workbench

Define Open Workbench Default Options

Define Open Workbench WBS Level Labels