Use the Calendar tab on the Resource Properties dialog box to assign a resource's vacations, holidays, or other periods of non-availability. If you are using Open Workbench with CA Clarity PPM, use this calendar only to perform what-if scenarios.
Note: Set all days as either work days or holidays.
To define a resource's calendar data
The General tab on the Resource Properties dialog box opens.
The resource's calendar data display.
The resource calendar inherits this calendar's working days, holidays, and shift settings.
Options: USA, United States, or United Kingdom
Default: USA
The selected day is highlighted.
All days for the selected day of the week are highlighted.
The resource is available according to its availability setting.
The resource is unavailable to work on the selected dates.
The Resource Properties dialog box closes.