Previous Topic: Define Resource Advanced Properties

Next Topic: Add Notes

Define Resource Calendar

Use the Calendar tab on the Resource Properties dialog box to assign a resource's vacations, holidays, or other periods of non-availability. If you are using Open Workbench with CA Clarity PPM, use this calendar only to perform what-if scenarios.

Note: Set all days as either work days or holidays.

To define a resource's calendar data

  1. From a view that displays the resource detail pane, right-click the resource and select Modify from the shortcut menu.

    The General tab on the Resource Properties dialog box opens.

  2. Click the Calendar tab.

    The resource's calendar data display.

  3. Select a calendar from the Based On pull-down.

    The resource calendar inherits this calendar's working days, holidays, and shift settings.

    Options: USA, United States, or United Kingdom

    Default: USA

  4. Do one of the following:
  5. Do one of the following:
  6. Click OK.

    The Resource Properties dialog box closes.

More information:

Update Resource Data

Edit Calendars