Move resource allocations back and forward in time to shift or scale all or a portion of the resource allocations in an idea. As you move data, segmented allocation dates are kept intact, even when the percent allocated for each segment changes. Shifting allocations is useful for projecting allocations beyond the allowable time-scaled view, which can only extend for six months.
For example, consider an allocation that starts on May 1, continues at its default rate of 100 percent through the end of May. Then goes through June at the reduced allocation of 50 percent. Now, shift the allocation to start from June 1 to July 2 (for 31 calendar days) at 100 percent, and up to August 2 at 50 percent. You can also shift allocations for time spans that contain no segments.
Follow these steps:
The staff list page appears.
The allocations page appears.