Previous Topic: Overview of Management Controls

Next Topic: Highlight Report Details

View PRINCE2 Reports

The PRINCE2 reports are categorized by the following types and are grouped by their corresponding tabs:

Follow these steps:

  1. Open the PRINCE2TM Management Controls menu, and click Select Reports.

    The highlight reports page appears by default listing the highlight reports for all PRINCE2 projects.

  2. Select the tab for a particular report type to display that report type for all PRINCE2 projects.

    The list page for the particular report type appears. By default, the contents on this page are sorted first by Project and then by Report Date. The following fields are available:

    Project

    Displays the name of the PRINCE2 project associated with the report. Click a project name to drill-down to the project properties page.

    Report Date

    Displays the date of creating the report.

    Report Name

    Displays the name of the report.

    Approval Status

    Displays the current approval status of the report.

    Project Manager

    Displays the project manager associated with the report.

    Submitted Date

    Displays the date of submitting the report for review.

    Period Covered

    Displays the period covered by the report.

    Start Date

    Displays the schedule start date from the project schedule page.

    End Date

    Displays the schedule end date from the project schedule page.

    PRINCE2 Stage

    Displays the current PRINCE2 stage of the associated project. The shaded area indicates the project stage. The color of the shaded area corresponds to the schedule Status field.

    Values:

    • SU. Starting up a Project
    • IP. Initiating a Project
    • CS. Controlling a Stage
    • SB. Managing Stage Boundaries
    • CP. Closing a Project

More information:

Highlight Report Details

Checkpoint Report Details

Exception Report Details