Tasks Portlet

The Tasks portlet displays the total amount of effort required to complete selected tasks. Tasks flagged for status reporting from the task properties page appears in the portlet. The portlet provides the following details:

Project

Displays the name of the associated project. Click the project name link to open the project properties page and edit the project.

Task

Displays the name of the associated task. Click the task name link to open the task properties page and edit the task.

Status

Indicates the status of the task.

Values: Started, Not Started, and Completed

Due Date

Displays the date for completing the task.

Days Late

Displays the number of days the task is late.

Total Effort

Displays the total ETC plus actuals for the task.

Schedule

Displays Gantt bars for a six-month period starting with the current month.

Gantt Bar Color Indicators: