Milestones Portlet

The Milestones portlet lists the incomplete project milestones, or tasks and how they affect the project schedule.

This portlet includes the following fields:

Schedule

Displays a stoplight indicating the project schedule based on the value in the Days Late column.

Stoplight Colors:
Project

Displays the name of the associated project. Click the project name link to open the project properties page and edit the project.

Milestone

Displays the name of the milestone. Click the milestone link to open the task properties page and edit the milestone.

Due Date

Displays the due date for the milestone to be complete. The due date is the baseline finish date for the milestone. If no baseline exists, is the finish date of the milestone.

Days Late

Displays the number of days past the baseline due date for the milestone. If the milestone is not late, a negative number displays indicating the number of days until the due date. For example, a negative five implies that five days are left before the task becomes due.