A task is considered late if it is past the baseline due date, or the finish date for the task (if the project was not baselined). A task is considered scheduled late when baseline due date is before the finish date for the task. This implies that the project was baselined and then the task date was moved out.
The Schedule Performance portlet displays the number of late tasks in a column graph format. Late tasks are categorized as follows:
If no columns appear on the graph, it means that all tasks are finishing as scheduled.
From the Schedule Performance portlet, click a column in the graph to open the Schedule Performance Details portlet for a list of the critical late, past due, or scheduled late tasks. This portlet displays the following details for that task group:
Displays the name of the associated project. Click the project name link to open the project properties page and edit the project.
Displays the name of the associated task. Click the task name link to open the task properties page and edit the task.
Indicates the status of the task.
Values: Started, Not Started, and Completed
Displays the task grouping.
Values: Critical Late, Past Due, and Scheduled Late
Displays the date when the task is scheduled to be completed.
Displays the number of days past the due date of the task, based on the current date.
Displays the total effort or ETC to complete the task.
| Copyright © 2011 CA. All rights reserved. | Tell Technical Publications how we can improve this information |