How to Work with Baselines (Microsoft Project)

You can save a baseline of the project from Microsoft Project or from CA Clarity PPM. You can keep a copy of the schedule now, or at any point, by saving a baseline.

The baseline is saved with the resources time-varying rate at the time a baseline revision takes place.

Note: You must have Project - Modify Baseline rights for the project to save a baseline.

Microsoft Project 2000

Microsoft Project 2000 can support only a single baseline.

When opening the project in Microsoft Project:

When saving the project to CA Clarity PPM, CA Clarity PPM Schedule Connect checks for baseline information. If the plan has:

Microsoft Project 2002 and later

Microsoft Project 2002 and later can support up to 11 baselines. Multiple baselines are managed by saving each revision to baseline slots in the .MPP file. For example, the information for the Current revision is saved to the baseline slot, a previous baseline revision is saved to the baseline1 slot, and so on up to baseline10.

When opening the project in Microsoft Project:

When saving the project to CA Clarity PPM, CA Clarity PPM Schedule Connect checks each possible baseline slot in the project, starting with the baseline slot and ending with the baseline10 slot: