You can assign resources to tasks from CA Clarity PPM or from Microsoft Project.
In CA Clarity PPM, you can assign resources to tasks from the following pages:
Resource assignments created in CA Clarity PPM default to the Default Load Pattern specified by the Project Management Settings in the Administration Tool.
When you open a CA Clarity PPM project in Microsoft Project, the following occurs:
|
Updating Task Status Updates Resource Status |
Split In-progress Tasks |
Work Contour set to |
|---|---|---|
|
Selected |
Not Selected |
Contoured |
|
Selected |
Selected |
Flat |
|
Not Selected |
Not Selected |
Flat |
|
Not Selected |
Selected |
Flat |
Note: If the project's Track Mode field in CA Clarity PPM is set to Clarity or Other, the Updating Task Status Updates Resource Status check box is cleared, regardless of the user settings in Microsoft Project.
The schedule for the work may change when opening the project in Microsoft Project.
Examples
If you create a Front-loaded assignment in CA Clarity PPM with 40 hours on a 5-day task, CA Clarity PPM schedules that work as full-time over those five days. Microsoft Project will schedule those 40 hours over 8.33 days.
If you assign a resource uniformly to a 5-day task in CA Clarity PPM and then change the task duration to 10 days, the rate of work is reduced to half-time, retaining the total amount of work. Microsoft Project reschedules this change as full-time, shortening the task back to 5 days.
Note: See the Project Management User Guide for more information.