The following access rights are required to create and manage projects using CA Clarity PPM with Open Workbench and with Microsoft Project:
To open a project
To create a project
To display resources and roles to which you have been granted access rights
To change the allocations of a resource
Note: You must have Hard Book rights to change the allocation of a resource who was hard-booked.
To set the baseline of a project:
If you are granted the Project - Modify Baseline right at the instance or organizational breakdown structure (OBS) level, you are implicitly granted the Project - Edit Management right. If you are granted the Project - Modify Baseline - All right at the global level, you are not granted the Project - Edit Management right. You must also explicitly be granted the Project - Edit right and the Project - Edit Management right to set the baseline.
Note: See the Project Management User Guide for more information.