You can update timesheets or financial transactions in CA Clarity PPM that may affect information on projects that you are updating. When a project is locked, most timesheets and transaction updates that affect a project are blocked.
The following changes are retained and merged when saving projects to CA Clarity PPM:
Note: The Project - Edit Project Plan access right is required.
When the project is saved to CA Clarity PPM, unplanned tasks and assignments are not deleted. Any unplanned tasks and assignments that you have open in a scheduler tool are marked as planned when they are saved to CA Clarity PPM. This enables you to delete unplanned tasks and assignments from the scheduler tool at a later time.
Note: Assignments are tracked when the Track Mode field in CA Clarity PPM for associated projects and resources is set to Clarity or Other. Actual, Actuals Thru Date, Pending Actuals and for Pending Estimates data (except for setting it to blank) is maintained from CA Clarity PPM. Any changes you make to these fields from Open Workbench or Microsoft Project are ignored.
| Copyright © 2010 CA. All rights reserved. | Email CA Technologies about this topic |