You define scheduling properties for the following purposes:
Best Practice: Set the percent complete calculation method at the beginning of your project and do not change it. Changing the method midway through the project changes the percent complete values for the project and tasks, which affects other calculations such as earned value metrics.
To define the scheduling properties for a project
The Project: Properties: Main - General page appears.
The Project: Properties: Main - Schedule page appears.
Defines the start date of the project.
Defines the finish date of the project.
Specifies whether to keep planned cost dates synchronized with the investment dates.
Default: Selected
Defines the date by which you want information to be included in time and budget estimates. This date is used in Earned Value Analysis (EVA) calculations, such as Budgeted Cost of Work Scheduled (BCWS).
Indicates the level of work that has been completed on project tasks. Use the following as a guideline:
Options: Completed, Started, and Not Started
Default: Not Started
Defines the percent of work that has been completed on the project based on the percentage of completion of the tasks and subprojects. This field is display only and system calculated if the % complete calculation method is set to duration or effort.
Default: 0
Values: 0 through 100
If you are using CA Clarity PPM with Open Workbench, defines the relative importance of this project in relation to all other projects. The priority controls the order in which tasks are scheduled during Autoschedule. The priority is subject to dependency constraints.
Values: 0-36, where 0 is the highest
Default: 10
Indicates the project's status.
Stoplight values:
Defines any comments about the project's status.
Specifies the method for calculating the percent complete value for the project and tasks.
Note: If you are using CA Clarity PPM with Microsoft Project or if your company uses an external job to calculate % Complete, select manual as the % complete calculation method.
Values:
Summary Task % Complete = Total Detail Task Duration Complete / Total Detail Task Duration
Summary Task % Complete = Sum of Detail Task resource assignment Actuals / Sum of Detail Task resource assignment Effort Detail Task % Complete = Sum of resource assignment Actuals / Sum of resource assignment Effort
Note: If you assign a resource other than labor to a task and the % Complete Calculation Method field on the scheduling properties page is set to Effort, the effort and actuals for that resource are ignored in the calculation.
Default: Manual
Your changes are saved.
| Copyright © 2010 CA. All rights reserved. | Email CA Technologies about this topic |