The BCWP Override field does not display on this page by default. Your CA Clarity PPM administrator can add this field to the page.
You can manually override BCWP for a specific task on the Task Properties page. If you choose an earned value calculation method—such as weighted milestones, milestone percent complete, or apportioned effort—for your task, you must manually enter the BCWP value for the task.
To manually override BCWP at the task level
The Task Properties page appears.
The task's earned value is defined.