Manually Update Earned Value Data from the Baseline Page

You can manually update your project's earned value data from the Project: Properties: Baseline page. This is one of the ways you can save a snapshot of your project's current earned value.

Note: You must have at least one baseline for the Update Earned Value button to display on the page.

To manually update your project's earned value data from the baseline page

  1. Open the project for which you want to calculate earned value.

    The Project: Properties: Main - General page appears.

  2. Select the Baseline subtab.

    The Project: Properties: Baseline page appears.

  3. Click Update Earned Value.

    A snapshot of your project's current earned value is saved.