You can manually update your project's earned value data from the Project: Properties: Baseline page. This is one of the ways you can save a snapshot of your project's current earned value.
Note: You must have at least one baseline for the Update Earned Value button to display on the page.
To manually update your project's earned value data from the baseline page
The Project: Properties: Main - General page appears.
The Project: Properties: Baseline page appears.
A snapshot of your project's current earned value is saved.