Manually Update Earned Value Data from the Task List

You can manually update your project's earned value data on the Project: Tasks: Task List page. This is one of the ways you can save a snapshot of your project's current earned value.

To manually update your project's earned value data from the task list

  1. Open the project for which you want to calculate earned value.

    The Project: Properties: Main - General page appears.

  2. Click Tasks tab.

    The Project: Tasks: Task List page appears.

  3. Click Update Earned Value.