Managing Tasks › Delete Tasks and Milestones
Delete Tasks and Milestones
You can delete tasks from the Project: Tasks: Task List page and the Project: Tasks: Work Breakdown Structure page. The following procedures details how to deleted tasks and milestones from the task list.
Before deleting a task, consider the following:
- Deleting a task does not delete the assigned resources.
- Deleting a task containing subordinates deletes only the top-level task. The subordinate tasks remain part of the project.
- You cannot delete tasks with actuals posted against them; instead, they are placed in a deleted tasks phase. The task's estimates are set to zero and its status is set to "Complete."
- Deleting a task containing subordinate key tasks can affect their schedule. When the schedule is affected, it is updated to accommodate the change.
To delete a task or milestone
- Open the project.
The Project: Properties: Main - General page appears.
- Select the Tasks tab.
The Project: Tasks: Task List page appears.
- Do one of the following:
- To delete one task, select the check box of the specific task you want to delete.
- To delete all tasks listed, click the Select All icon.
- Click Delete.
The Delete Confirmation page appears listing the task to be deleted.
- Click Yes to confirm the prompt.
The task is deleted.