Use the Project: Risks/Issues/Changes: Change Requests page to create new change requests. If you have not created any change requests or had any assigned to you, then none appear in the list of Project Change Requests.
To create a change request
The Project: Properties: Main - General page appears.
The Project: Risks/Issues/Changes: Risks page appears.
The Project: Risks/Issues/Changes: Change Requests page appears.
The Create Change Request page appears.
Enter short name for the request
Limit: 64 characters
The unique identifier assigned to the request for tracking. This number must be unique. Once the risk is saved, the request ID cannot be changed.
Enter a short description of the request.
Select the category to which this request is assigned. Choices are Flexibility, Funding, Human Interface, Implementation, Interdependencies, Objectives, Organizational Culture, Resource Availability, Schedule Risk, Sponsorship, Success Risk, Supportability, or Technical.
Select an owner to manage the request. This resource is responsible for ensuring that the request is managed and tracked appropriately through its lifecycle. If an issue or change request is created from this risk, for example, the owner information is carried over to the issue or change request.
Select the status of this request.
Values: Open, Work in Progress, Closed, or Resolved.
This read-only field displays the name of the resource who created this request.
This read-only field displays the date this request was created.
This read-only field displays the name of the resource who last updated this request.
This read-only field displays the date this request was last updated.
Enter the reason(s) for the requested change.
Select the priority level of this request. Choices are Low, Medium, and High.
Select the date by which you expect to close the request.
Select the date this by which you want the next review for this request to occur.
Enter a close date for the request.
Describe how the changes in this request will impact the project's baseline, if at all.
Describe how this request will impact other projects, if at all.
Describe how this change will benefit the project.
Enter an amount by which you think this request will change the budgeted cost of the project.
Enter the number of days by which this request will delay or hasten the overall project schedule.
Enter a number that reflects the request for an increase or decrease in the number of resources needed for the project.
Click Browse to select the resource responsible for assessing this request.
Select the date by which the request should be assessed.
Click Browse to select the resource responsible for approving this request.
Select the date by which the request should be approved.