The baseline you create last becomes the current project baseline, by default. If you have defined only one baseline, this baseline is marked as the current baseline.
To define which baseline is current
The Project: Properties: Main - General page appears.
The Project: Properties: Baseline page appears.
The Baseline Revision Properties page appears.
The baseline revision is saved as the current baseline.