Define which Baseline is Current

The baseline you create last becomes the current project baseline, by default. If you have defined only one baseline, this baseline is marked as the current baseline.

To define which baseline is current

  1. Open the project.

    The Project: Properties: Main - General page appears.

  2. Click the Baseline subtab.

    The Project: Properties: Baseline page appears.

  3. Open the baseline you want to be current.

    The Baseline Revision Properties page appears.

  4. Select the Current Revision field, and then click Submit.

    The baseline revision is saved as the current baseline.

More information:

Edit Baselines