You can update existing project baselines to reflect changes to task assignments and other information. For example, you might want to update an existing baseline to include data from recently posted actuals. When you update a baseline, it becomes the current baseline revision.
When you update a baseline from the project, all of the changes you made to task assignments, estimates, and budgets since the last update are included. Updating a baseline changes its values accordingly.
When you update a master project's baseline, you also update the baselines for each subproject listed in the master project's subproject hierarchy. This baseline becomes the current baseline for the master project and its subprojects.
When you update a subproject's baseline, baseline and earned value data are not rolled up. You must initiate the update from the master project in order to roll up baseline data through the master project's subproject hierarchy.
Note: When you initiate an update from the master project, only the subproject’s that you have marked as Read/Write are updated.
Use this procedure to manually update master project and subproject baselines.
To manually update a baseline at the project level
The Project: Properties: Main - General page appears.
The Project: Properties: Baseline page appears.
The Confirm Revision Update message appears.
The updated project baseline displays on the Project: Properties: Baseline page.