Indent and Outdent Tasks in Work Breakdown Structure

You can create hierarchical relationships between tasks. Indent a task to make it a child of the task above it.

Use the Indent or Outdent links to designate individual tasks as parent or children. Parent tasks are top-level tasks that have child tasks associated with them. Child tasks are nested beneath parent tasks. The task above it in the hierarchy can be a top-most task, or a second-, third-, or fourth level task relative to the task above it. You can create an unlimited number of hierarchy levels on the work breakdown structure.

Rules for Indenting and Outdenting

To indent or outdent a task

  1. Open the project.

    The Project: Properties: Main - General page appears.

  2. Select the Tasks tab.

    The Project: Tasks: Task List page appears.

  3. Select the Work Breakdown Structure subtab.

    The Project: Tasks: Work Breakdown Structure page appears.

  4. Select the task you want to indent or outdent, click WBS Layout>>, and do one of the following:

    The task is indented or outdented.