Update Earned Value Totals Job

The Update Earned Value Totals job tracks project progress by calculating earned value and updating costs. This job invokes the Update % Complete job before it runs and completes. Calculates and records the project's current earned value data totals through the current date for a project or set of projects based on the parameters you select. The data is stored in a reserved row in the PRJ_EV_HISTORY (earned value history) table. The saved current earned value data totals are displayed in fields on projects and tasks.

This job is scheduled to run regularly. You can schedule this job to run in the background. You can invoke this job on demand from within the project by updating the earned value.

Note: See the Project Management User Guide for more information.

Restrictions

This job cannot run concurrently with any other instance of the Update Earned Value Totals job.

Parameters

The following parameters are provided:

Note: If you do not complete any of the parameters, then all projects are processed.

Project

Defines the name of the project.

OBS Unit

Defines the name of the OBS Unit.

Project Manager

Defines the name of the project manager.

More information:

Update % Complete Job