Text3 is for Resource, Project, Task, and Assignment. It is used for information that is required by CA Clarity PPM Schedule Connect. If Text3 is used for another purpose in your organization, change the mapping.
Relevant mapping is for PRUID. It must be mapped somewhere; do not remove it without remapping. These mappings are system-wide. You cannot remap Text3 on one project and keep the same on other projects.
Text4 is for Task work breakdown structure (WBS). It is used internally by CA Clarity PPM Schedule Connect to order the WBS when opening the project in Microsoft Project. You cannot remap this field.
|
Microsoft Project |
CA Clarity PPM |
Notes |
|---|---|---|
|
Custom property/prVersion |
PRJ_PROJECTS: PRVERSION |
Sets the version (internal use only) when opening the project in Microsoft Project and when saving back to CA Clarity PPM. |