When you commit planned allocation you set the hard allocation to be equal to the planned allocation. When a resource has a hard booking status, that resource is fully committed. Committing planned allocation does not reset the default allocation percentage; it copies the planned allocation into the Hard Allocation section of the Project: Team: Staff page.
The Hard Allocation section of the page displays on the page depending on your project management Mixed Booking settings.
Note: Contact your CA Clarity PPM administrator or see the Administration Guide for more information..
To commit all planned allocation
The Project: Properties: Main - General page appears.
The Project: Team: Staff page appears by default.
The Update Allocation Confirmation page appears..
The resource's planned allocation is committed.