View ETC

Use the Project: Properties: Main - Estimating page to view and edit the combined ETC of all the tasks in the project. The Current ETC column displays the system-generated combined ETC for all of the tasks in each phase of the project.

To view the ETC for each task in the phase or group, click the Plus icon in front of a task grouping. A task grouping refers to any group that consists of a top-level task and its subordinates.

Important! Resources must be assigned to tasks in order to modify and view ETC.

To view generated ETC

  1. Open the project.

    The Project: Properties: Main - General page appears.

  2. Click Estimating from the content menu.

    The Project: Properties: Main - Estimating page appears.

  3. Click Preview.

    A breakdown of project ETC by phase or task grouping is displayed. This lists the ETC for each task grouping.

More information:

Estimates (ETC) at the Project Level

How to Define Project Estimates

How Estimates (ETC) are Calculated

How to Modify ETC at the Project Level