Building Project Teams › Staff Project Tasks › How to Replace Staff Assigned to Projects or Tasks › Role Replacement Behavior
Role Replacement Behavior
Consider the following behavior when replacing roles:
When a role is fully decremented by replacement with one named resource, the following behaviors are seen:
- The role's allocation is decremented to zero and the role is removed from the team list.
- All assignments and ETC that were assigned to the role are transferred to the named resource.
- The role's allocation is added to the named resource's allocation. In this case, it is possible to overallocate the named resource (that is allocate at greater than 100%).
When a role is partially replaced by one or more named resources, the following behaviors are seen:
- The role's allocation is decremented by the amount being replaced and the role remains on the team list.
- No transfer of assignments is made to the named resources.
- The amount of the replaced role allocation is added to the named resource's allocations.
When a role has assignments with ETC and is replaced so that the allocation is zero, the role remains on the team list. You should manually re-assign the task to the appropriate named resources and then manually remove the role from the team list.