Edit Work Packages

You must have the Contract - Edit access right to the work package's associated contract to edit work packages.

To edit a work package

  1. Open the work package.

    The Work Package: Properties page appears.

  2. Edit the following fields:
    Work Package Name

    Defines the work package's name.

    Work Package ID

    Defines the work package's unique identifier.

    Work Package Type

    Defines the work package's associated cost element. Typically, the type is a planning work package;. However, you can select any type as appropriate.

    Values: Labor, Sub-Contracted Labor, Material, Sub-Contractor, Other Direct Costs, Planning Package, and Project

    SOW Number

    Defines the Statement of Work (SOW) number.

    CLIN

    Defines the Contract Line Item Number (CLIN).

    CLIN Status

    Defines the Contract Line Item Number (CLIN) status.

    Values:

    • Authorized – Definitized. Defines authorized work on which contractual agreement has been reached.
    • Authorized - Not Definitized. Defines work, such as additional agreements or changes, for which firm contract prices have not yet been agreed to in writing by the parties to the contract.
    • Forecast - Not Yet Authorized. Defines changes that are proposed by the U.S. federal government agency or by the contractor, but not yet directed by the contracting officer.
    • Forecast - All Other Work. Defines additional work anticipated to be performed, but not included in a firm proposal, which the contractor, based on his knowledge and experience, expects to submit to the U.S. federal government agency within a reasonable period of time.
    Start Date

    Defines the work package's planned start date.

    Finish Date

    Defines the work package's planned finish date.

  3. Click Submit.

    Your changes are saved.