Calculate Earned Value Metrics on Contracts

You can calculate historical earned value metrics based on the contract's associated earned value reporting period. You can update your contract's current earned value metrics at any time. You can do this manually or you can schedule the Update Earned Value Totals - Contracts job to run at regularly scheduled times. Both methods refresh the earned value (EV) metrics that are displayed on CWBS elements, control accounts, and work packages.

The earned value reporting period defines the frequency and the interval for the Update Earned Value History - Contracts job to take historical earned value snapshots of performance and save snapshot in the earned value history table.

Note: See the Administration Guide for more information.

More information:

Update Earned Value History - Contracts Job

Update Earned Value Totals - Contracts Job