Previous Topic: Program Freezer

Next Topic: Merging Freezer Information

Change Program Freezer Database

You can change the existing freeze data to reflect changes in a program’s data set, member, or volume names.

To modify the freezer database

  1. From the Primary menu select option 5.

    The Program Information menu is displayed.

  2. Select option 5.

    The Program Freezer options are displayed.

  3. Select option 2.

    The Change Program Freezer Database panel is displayed.

  4. Press Enter.

    The Programs To Change In Freezer panel is displayed.

  5. Use this panel to add the changes to the CA Auditor freezer database.