Edit Task Properties

You can edit task properties on the Sprint Backlog & Charts page.

Follow these steps:

  1. On the Sprint Backlog & Charts page, expand the parent user story and click Edit for the task you want to edit.
  2. Complete the following fields:
    Title

    Defines the name of the task.

    Required: Yes

    Status

    Specifies the current state of the task.

    Values:

    • Planned
    • In Progress
    • Completed
    • Closed

    Default: Planned

    Assignee

    Specifies the team member assigned to the task.

    Team

    Specifies the scrum team assigned to complete the task.

    Estimated Hours

    Defines the number of hours estimated to complete the task including hours already logged for the task.

    Type

    Defines the task type.

    Values:

    • Implementation
    • QA
    • Doc
    • Design
    • Other

    Default: None

  3. Click Save.

    The task properties are updated and you are returned to the Sprint Backlog & Charts page.

To edit task properties from the User Story Detail page

  1. With the User Story Detail page open, click Edit next to the task you want to edit.

    The Task Edit page appears.

  2. Modify the following fields:
    Title

    Defines the name of the task.

    Required: Yes

    Status

    Specifies the current state of the task.

    Values:

    • Planned
    • In Progress
    • Completed
    • Closed

    Default: Planned

    Description

    Defines the purpose of the task and provides additional relevant information.

    Assignee

    Specifies the team member responsible for completing the task.

    Default: The assignee for the user story, if specified.

    Type

    Defines the task type.

    Values:

    • Implementation
    • QA
    • Doc
    • Design
    • Other
    Estimated Hours

    Defines the number of hours estimated to complete the task. This includes hours already logged for the task.

    Hours Worked

    Displays the number of hours already logged for the task.

    Team

    Specifies the scrum team assigned to complete the task.

    Default: The scrum team assigned to the user story, if specified.

  3. Click Save.

More information

Edit a Task on the Virtual Wall